FMG – Cloudbreak

Client: FMG Cloudbreak
Project: Lefthander Conveyance Main

Scope:

  • Clear and grub 8.5 hectares for pipe corridor, access track and fire break
  • Installation of HDPE pipeline consisting of 4,200m of DN630 HDPE pipe
  • Installation of 20 pipe burials
  • Construction of 4 Flushing Bunds
  • Flushing, hydrostatic testing and commissioning of piping infrastructure

Key Equipment:

  • Earth Moving Equipment:
    • 40t Moxy Dump Truck
    • D8 Bulldozer
    • 24t Excavator
    • 33t Excavator
    • L90 Loader
    • Z80 Loader
    • Z70 Loader
    • 12m Grader
    • Skid Steers
  • Heavy Vehicles:
    • Various Light Vehicles
    • 6×4 Tippers
    • Service Trucks
    • Water Carts
    • 20t Franna
    • Canter Crew Truck
  • Welding Equipment:
    • McElroy T900 Welders
    • Veitz VFT900 Welder
  • Ancillary Equipment:
    • Office Blocks
    • Crib Rooms
    • Toilet Blocks
    • Water Tanks
    • Genset – General 6KVA
    • Genset – Dixon 12.5KVA
    • Genset – Back up 13KVA

Related Projects

ROY HILL – Project Completion

Client: Roy Hill Services: Project Completion Project: Mainline 2 Extension & In Pit Saline Connector Scope: Clear and grub pipe alignment 300m of DN800 PN10 HD...

READ MORE

Rio Tinto – Yandicoogina

Client: Rio Tinto Services: Yandicoogina Project: Oxbow Scope: Design management, supply and install 8 x bore dewatering headworks trailers Supply and install...

READ MORE