Plummers Project Services Complete Roy Hill Project – Mainline 2 Extension & In Pit Saline Connector

Project was completed on time, within budget and with zero incidents. Team worked closely with site team to coordinate time critical isolations, which were executed without a hitch.

Project was key to maintaining mining operations.

Scope of Works:

  • Clear and grub pipe alignment
  • 300m of DN800 PN10 HDPE Pipeline & associated fittings
  • 100m of DN250 PN10 HDPE Pipeline & associated fittings
  • 3000m of DN360 PN10 HDPE Pipeline & associated fittings
  • Supply & installation of all valves
  • Add in four connections to existing pipeline
  • Pipeline burials for seven track/road crossings
  • Installation of flow meter, Telemetry panel and cabling

For more information on our Project Services, please contact projectservices@plummers.com.au.